The City of Coral Springs awarded a contract to Sports Facilities Development, LLC (SFC) of Clearwater, Florida for the Facility Optimization & Recreation Master Planning Service to develop a piece of vacant land located behind the Aquatics Complex on Sportsplex Drive for state-of-the-art gymnasium facility to include sports courts, track, bleachers, fitness center, locker rooms, and additional multi-purpose amenities. The firm will reimagine the current Aquatic Complex and Tennis Center sites to enhance functionality and aesthetics. This is to serve as a world class facility for sports activities, community events, and competitions. 

Project Timeline:

  • 2022-2024: Create a Destination Attraction in the Sportsplex, identified as an opportunity and added to the city’s Strategic Plan.
  • February 21, 2024: LOI Issued
  • May 1, 2024: Proposal Presentations
  • June 5, 2024: Award of Contract
  • October 2025: Presentation of Master Plan options provided to the City Commission for consideration.
  • January 2026: City Commission approved an amendment to the agreement designating SFC as the Owner’s Representative for the Sportsplex Optimization project.
  • February 2026: Sportsplex Optimization updated to the city’s Strategic Plan.
  • March 2026: Development Review Committee (DRC) application submitted for the project.
  • March 26, 2026: LOI #26-A-201 process began for Professional Architecture/Engineering Design Services.
  • June 2026 - PBK Architects selected by the review committee for LOI #26-A-201 Professional Architecture/Engineering Design Services.
  • July 2, 2026 - An agreement with Sports Facilities Companies was approved by the City Commission to allow for SFC to explore naming rights and sponsorships for the project.
  • Fall 2026 - Community Engagement Meetings scheduled for September 26 and October 14. 

Project Costs

  • Budgeted to Date: $1,795,500