SR817-University Drive Mobility Improvement Project

  • Project typeFDOT Project
  • Project value$13,651,000
  • Project scheduleJanuary 2023 - Summer 2024

PROJECT IMPROVEMENTS 

map

  • Widening the roadway to accommodate two additional travel lanes and to increase the bike lanes from 4-feet to 7-feet from NW 40th Street to SR-869/Sawgrass Expressway 
  • Relocating existing 6-foot sidewalk from NW 40th Street to SR-869/Sawgrass Expressway 
  • Relocating impacted drainage structures 
  • Regrading swales to ensure proper drainage flow 
  • Upgrading traffic and pedestrian signals at NW 40th Street and Westview Drive 
  • Installation of 77 light poles along the project corridor 
  • Milling and resurfacing within the project limits 
  • Upgrading curb ramps, signing, and pavement markings 

 

TRAFFIC IMPACTS

  • Lane closures along SR-817/University Drive (from NW 40th Street to SR-869/Sawgrass Expressway), Wiles Road, and Westview Drive may occur during non-peak hours from 10 p.m. to 6 a.m. 
  • NW 38th Drive will be closed during utility operations. Traffic will be detoured using SR-838/Sample Road, NW 85th Avenue, NW 38th Street, NW 84th Avenue, NW 40th Street, and SR-817/University Drive. 
  • NW 38th Street will be closed during utility operations. Traffic will be detoured using Broken Woods Drive. 
  • Business and residential access will be maintained at all times throughout construction. 